No. | Name | Start | End | Duration |
1. | Alpha Infrastructure Change Freeze | Tue 2012-02-14 | Tue 2012-02-28 | 14 |
2. | Alpha Public Availability | Tue 2012-02-28 | Tue 2012-02-28 | 0 |
3. | Beta Infrastructure Change Freeze | Tue 2012-03-20 | Tue 2012-04-17 | 28 |
4. | Beta Release Public Availability | Tue 2012-04-17 | Tue 2012-04-17 | 0 |
5. | Final Infrastructure Change Freeze | Tue 2012-05-08 | Tue 2012-05-29 | 21 |
6. | Final (GA) Release | Tue 2012-05-29 | Tue 2012-05-29 | 0 |
Version 17 - Created on 2012-Aug-02 with TaskJuggler v2.4.1