| 1. |
Fedora 18 |
Wed 2012-05-09 |
Fri 2013-02-15 |
282.8 |
| 2. |
Testing Phase |
Wed 2012-05-09 |
Fri 2012-12-21 |
226.8 |
| 3. |
Alpha Release |
Wed 2012-05-09 |
Tue 2012-11-06 |
181.8 |
| 4. |
FAmSCo and Regional teams call for Preparation of Media/SWAG |
Thu 2012-09-27 |
Thu 2012-09-27 |
0 |
| 5. |
FAmSCo heads Ambassador Wide Meetings Preparing For Fedora 18 |
Thu 2012-09-27 |
Thu 2012-10-04 |
7 |
| 6. |
Regional Team Meetings and Select POC for Swag/Media production |
Fri 2012-09-28 |
Fri 2012-10-05 |
7 |
| 7. |
Regional Teams Submit Funding Request For Swag/Media Production |
Fri 2012-09-28 |
Fri 2012-10-05 |
7 |
| 8. |
Beta Release |
Wed 2012-05-09 |
Fri 2012-12-21 |
226.8 |
| 9. |
FAmSCo Coordinate Media/Swag/Poster artwork with Design team |
Mon 2012-11-12 |
Mon 2012-11-26 |
14 |
| 10. |
FAmSCo and Regional Teams Call for Release Events |
Thu 2012-11-29 |
Thu 2012-11-29 |
0 |
| 11. |
Regional Teams Plan Regional Logistics for Release Events & File Budget Requests |
Thu 2012-11-29 |
Thu 2012-12-13 |
14 |
| 12. |
FAmSCo Regional IRC town halls |
Fri 2012-12-07 |
Fri 2012-12-21 |
14 |
| 13. |
Release Event Submission Deadline |
Fri 2012-12-14 |
Fri 2012-12-14 |
0 |
| 14. |
FAmSCo Review Budget Allocations |
Fri 2012-12-14 |
Fri 2012-12-14 |
0 |
| 15. |
Launch Phase |
Wed 2012-05-09 |
Fri 2013-02-15 |
282.8 |
| 16. |
Release Candidate |
Wed 2012-05-09 |
Mon 2013-01-21 |
257.8 |
| 17. |
FAmSCo and Regional Teams Meet to Address Unresolved Events/Media/Swag Issues |
Wed 2012-12-19 |
Wed 2012-12-19 |
0 |
| 18. |
Regional Teams Obtain Final Release ISOs from Release Engineering for duplication |
Thu 2013-01-10 |
Tue 2013-01-15 |
5 |
| 19. |
Regional Coordination with Marketing for Release Events |
Thu 2013-01-10 |
Thu 2013-01-17 |
7 |
| 20. |
Release Party Posters |
Tue 2012-11-27 |
Mon 2012-12-24 |
27 |
| 21. |
FAmSCo with Design Team Create Release Party Posters |
Tue 2012-11-27 |
Tue 2012-12-11 |
14 |
| 22. |
Hold Release Events and Publish Event Reports |
Tue 2013-01-15 |
Fri 2013-02-15 |
31 |